Structural Revisions That Delay Your Projects
16, May 2025
When the Permit Office Fights Back: Structural Revisions That Delay Your Projects

When the Permit Office Fights Back: Structural Revisions That Delay Your Projects is a frustration every developer or contractor dreads. Just when you’re ready to build, the city says, “Not so fast.”

Even small structural concerns can lead to weeks—or months—of delay. And the longer the project sits, the more costly it becomes.

When the Permit Office Fights Back: Structural Revisions That Delay Your Projects explores why revisions happen, what causes red flags, and how you can prevent permit setbacks with smarter structural design.


Why Permits Matter More Than Ever

City permit offices are stricter than ever. As codes evolve, enforcement grows tighter. Local authorities are watching for:

  • Seismic safety.
  • Wind loads.
  • Foundation stability.
  • Material standards.
  • Energy codes tied to structural components.

Failure to meet even one detail can halt your entire project.


Top Structural Issues That Trigger Permit Rejections

1. Incomplete or Vague Structural Calculations

Missing load paths, unclear connections, or unverified assumptions will raise red flags with reviewers.

2. Incorrect Load Assumptions

Using outdated or regional load values (wind, snow, seismic) is a common mistake—especially for multi-state builders.

3. Improper Foundation Design

Expansive soils, unverified geotechnical assumptions, or poor detailing can cause rejections.

4. Missing Details on Framing or Connections

Building officials want clarity. Generic notes or “TBD” tags often trigger requests for more information.

5. Non-compliance With Local Amendments

Even if the plans meet IBC standards, local codes may require additional measures. Overlooking these leads to delays.


When the Permit Office Fights Back: Real Consequences

The true cost of structural revisions isn’t just the redesign fee. It includes:

  • Lost time (weeks to months).
  • Resubmission fees.
  • General conditions on hold (trailers, crews, inspections).
  • Penalties for missed start dates.
  • Tenant or client dissatisfaction.

Preventing these delays starts with better engineering up front.


The Role of a Structural Engineering Company

A qualified structural engineering company knows how to design for both strength and compliance.

They provide:

  • Accurate load calculations.
  • Foundation solutions based on soil reports.
  • Full detailing for beams, connections, and lateral systems.
  • Coordination with MEP, architectural, and civil teams.
  • Plan sets ready for permit review.

This reduces back-and-forth with reviewers and speeds approvals.


Why Local Experience Matters

Not all cities read the same set of rules. That’s why a structural engineering firm familiar with local codes is a major asset.

Texas, Florida, and California each have unique requirements. Even cities within the same state may differ.

Hiring an out-of-state engineer unfamiliar with local amendments often leads to revisions, resubmittals, and frustration.


Common Reviewer Comments on Structural Plans

Permit reviewers tend to raise concerns such as:

  • “Provide calculations for lateral loads.”
  • “Clarify anchorage at base of shear wall.”
  • “Details for beam-to-column connections missing.”
  • “Reconcile discrepancy between plan and elevation.”
  • “Verify uplift resistance in foundation.”

These are common. A seasoned engineer can address them before the reviewer ever sees the plan.


Coordination with Other Disciplines

Many structural revisions are caused by lack of coordination. Typical conflicts include:

  • HVAC ducts cutting through structural joists.
  • Plumbing or fire risers not accounted for in slab design.
  • Architectural overhangs missing proper support framing.

A skilled structural engineering company works closely with architects, MEP teams, and civil engineers to ensure alignment across all trades.


How to Prevent Structural Permit Delays

1. Get Geotechnical Reports Early

Don’t guess on soils. Provide actual data so foundations can be properly sized and justified.

2. Involve Engineers in Design Development

Don’t wait until 90% design to bring in your structural team. Early input avoids major changes later.

3. Use Local Engineering Talent

Choose a firm that has worked in the same city or county. They’ll know what reviewers expect.

4. Submit a Clean, Complete Package

Missing sheets, unsealed plans, or PDF errors can trigger automatic rejection. Always double-check before submission.


When Revisions Are Inevitable: What to Do

Sometimes, even well-prepared plans get kicked back. Here’s how to respond effectively:

  • Address each reviewer comment directly, point-by-point.
  • Provide new calculations or drawings that clearly solve the issue.
  • Don’t argue—respond with data, not opinion.
  • If needed, request a meeting with the reviewer to clarify the solution.

Your structural engineering company should take the lead on this, drafting responses and preparing revised plans quickly.


How MEP Design Engineering Can Impact Structural Permits

Yes—MEP systems can affect your structural permit. Here’s how:

  • Rooftop equipment impacts structural loads and seismic bracing.
  • Suspended mechanical units must be accounted for in ceiling framing.
  • Plumbing and fire lines may penetrate shear walls or structural slabs.

A MEP engineering company that collaborates early with structural engineers helps avoid these costly oversights.


Customized Solutions for Challenging Projects

Tight sites, unique soil conditions, or unusual building shapes often require customized structural solutions. These may include:

  • Special foundations (micropiles, grade beams).
  • Lateral systems for narrow or irregular buildings.
  • Hybrid materials (steel and wood).
  • Reinforcement for future vertical expansion.

These designs are more complex—but easier to permit when engineered with precision and clarity.


Final Thoughts

When the Permit Office Fights Back: Structural Revisions That Delay Your Projects is a reality every builder faces. But it doesn’t have to derail your timeline.

Success comes from planning, clarity, and expert coordination. A proactive structural engineering company can prevent most delays before plans ever reach the city.

Combined with an aligned MEP engineering company delivering customized MEP solutions for building design and energy-efficient MEP design engineering, you can get your permits faster—and build with confidence.

Don’t let the permit office catch you off guard. Build it right, the first time.